How we price schedule certainty: a 2–4% premium, delay damages capped at 10%.
.avif)
Kestrel Power competes on schedule certainty and ESI depth, not on the lowest price. For that to be honest, the price of certainty has to be stated.
Our planned schedule certainty premium is 2–4% of contract value, with liquidated damages capped at 10% of contract value and retention at 5%.
What the premium buys
The premium pays for a named commissioning lead from award, early long-lead orders, witnessed factory acceptance tests, the weekly float report and owned test equipment. Packages run from $2m to $60m in four forms: design and construct ($10m–$60m), construct-only ($2m–$30m), panel and schedule of rates (panel $3m–$10m a year) and maintenance and testing ($150k–$1.5m a year).
A premium we cannot explain line by line is a premium we should not charge.
Kestrel Power · Pricing principle
Where a client prefers a lower price and accepts schedule risk, we expect to say so in the offer and price accordingly.
Why the cap is 10%
An uncapped delay exposure cannot be insured or financed by a new contractor, and clients are better served by a cap Kestrel can stand behind. Planned insurances include $20m public and products liability and $10m professional indemnity, rising to $20m before any design and construct package above $40m.
Certainty is a commitment we can honour, so it has a limit.
Kestrel Power · Pricing principle