A 132 kV customer switchyard at Ipswich, planned for self-performed delivery.
Delivery brief
.
21 Nov 2026

A 132 kV customer switchyard at Ipswich, planned for self-performed delivery.

Placeholder portrait image, not a real person
Kestrel Power planning team
Illustrative delivery brief — not a completed project

Client

None (illustrative)

Sector

Data centre

Scope

132 kV customer switchyard

Region

Ipswich, Qld

A 132 kV package is lost in its interfaces.

Assumption: a customer at Ipswich needs a 132 kV AIS switchyard with an earth grid designed to ENA EG-1. Steel, foundations and cranes are subcontracted, and 132 kV cable jointing is done by OEM jointers. Protection, control, testing and commissioning are the scope Kestrel self-performs.

The exposure is the interfaces. Subcontractors, OEM jointers and the network service provider approvals all sit on one critical path. This brief is a planning scenario, not a completed project.

Programme · 132 kV switchyard
Illustrative, not measured

Own the interfaces, subcontract the heavy work.

Kestrel would hold the programme and the interfaces: a named commissioning lead from award, one Site Supervisor, and a weekly float report that shows subcontractor and OEM deliveries beside outstanding network approvals.

Earth grid verification, primary and secondary injection and protection testing would use Kestrel-owned test sets, so testing does not wait on hired equipment.

What the plan targets.

Assumptions, not results: a design and construct form with a schedule certainty premium of 2–4%, delay damages capped at 10% of contract value and 5% retention. The target is energisation on the contracted date, with every figure below a commercial term rather than a measured outcome.

2–4%
Schedule certainty premium
10%
Delay damages cap
5%
Retention

Where it would repeat.

A first switchyard would be a reference for the next one at the same site or a neighbouring precinct. That is intent only: there is no client, no contract and no completed work behind this brief.