the plan

Kestrel Power (year-one plan).

90
staff
Planned headcount, end of month 12
Year-one revenue
$26m
Owned test equipment
$1.39m
Depot area
8,000 m²
Q4 run-rate
$48m / yr
Milestone (plan)
target
Qld electrical contractor licence, before trading
Jan 2027
Powerlink pre-qualification: application
Jan 2027
Energy Queensland provider: application
Feb 2027
ISO 45001 / 9001: stage 1 audit
May 2027
Powerlink pre-qualification: approval targeted
Jun 2027
ISO 45001 / 9001: certification targeted
Sep 2027
Close-up of two high-voltage insulators attached to metal framework and electrical cables.