Five phases. Five exit gates.

Five phases take a package from design interface to handover, each closed by an exit gate. A named commissioning lead is on every project from award.

Isometric schematic of a zone substation
Schematic · zone substation
Rev 2026.07
phases 1 and 2

10

days
Long-lead plant ordered, business days after design freeze
The problem

Late design changes and late plant orders push out the energisation date. Long-lead plant sets the critical path.

Our answer

Design interface reviews at 30, 60 and 100%, with the commissioning lead signing. Long-lead plant is ordered within 10 business days of design freeze and witnessed at FAT, so the date is protected before anyone is on site.

Phases
1 and 2
Exit gate
100% design review signed
Standards
ENA EG-1
Build & commission

30

days
Readiness review before energisation
The problem

On site, one missed shutdown or network approval slips the whole programme. Approvals and outages are routinely the constraint.

Our answer

One Site Supervisor per site, a Friday three-week look-ahead and a weekly float report. A readiness review 30 days before energisation checks protection settings, plant, approvals and test records.

Phases
3 and 4
Exit gate
Readiness review passed
Standards
NER Chapter 5
Isometric technical diagram of an industrial building with internal piping, machinery, and electrical panels.
Schematic · site execution
Rev 2026.07
Isometric technical diagram of a city grid with three highlighted buildings connected by a white network.
Schematic · handover records
Rev 2026.07
Handover

30

days
Post-energisation support, days
The problem

An energised asset is only useful if its records are complete. Missing settings files and test records cost months later.

Our answer

As-builts, test records and relay settings files are handed over complete, and the team supports the asset for 30 days after energisation. Maintenance and testing work can follow from the same crew.

Phases
5
Exit gate
Handover pack complete
Standards
AS 2067:2016
Phase matrix

One delivery model. Three stages.

Design & procure
Build & commission
Handover
Phases
1 and 2
3 and 4
5
Exit gate
100% design review signed
Readiness review passed
Handover pack complete
Key control
Long-lead ordered in 10 days
Review 30 days out
30-day support
Named lead
Signs 100% review
Runs readiness review
Signs handover pack
Standards
ENA EG-1
NER Chapter 5
AS 2067:2016
Evidence
FAT witnessed
Weekly float report
Settings files issued